Before a single stand is bolted down, a roll forming line has already met its most important tooling: the concrete underneath it. A foundation that settles unevenly cannot be corrected at commissioning, so the civil package deserves the same attention as the mill itself.
Pour One Continuous Slab
Separate pads under each stand are the most frequent civil error. They settle at different rates, opening roll gaps on one side and twisting the strip. Cast the whole line in one pour. A 24 m line typically needs a slab 26 to 28 m long and 1.6 to 2.2 m wide, with a 20 mm isolation joint around the perimeter to keep building column movement out of the alignment.
Grade and Thickness by Load
C30/37 at 28 days covers most light and medium lines. C25/30 suits a small trim line under 6 t; C35/45 suits heavy gauge lines above 22 t. At 150 kPa soil bearing, use 200 mm for a light line, 250 mm for a standard purlin or cable tray line, 300 mm for a heavy rack line and up to 400 mm with a flying shear. Reinforcement is two layers of 12 to 16 mm bars at 150 to 200 mm centres.
Anchors From the Base Plate Drawing
Anchor positions come from the machine supplier, with ±2 mm tolerance on offset from line centre. Use M16 to M24 bolts, embedment of 12 to 15 times bolt diameter and pockets 100 to 150 mm square. Leave 25 to 50 mm of non-shrink grout under each base plate, poured only after the line is levelled. Re-torque at 7 days and again at 28 days.
Isolate Only What Needs It
Forming loads are steady; punching and cutting loads are not. Put 10 to 20 mm elastomeric pads under the punch and cut off press only. Isolating the forming stands lets roll gaps drift between modules. Flatness targets are 2 mm over any 3 m and ±1 mm end to end, with a 1 to 2 percent drainage fall cast in before the pour.