Where Do the Hours Go on an Upright Line?
An upright rack line can run from the first minute to the last and still deliver only 5.2 to 6.1 hours of good columns in an 8-hour shift. That is a typical OEE of 55 to 70 percent. The missing hours rarely come from one dramatic breakdown.
Six Small Losses, Two or Three Hours
The loss spreads across six places: coil changes, punch die regrinds, punch jams, style changeovers, straightener rework and line starvation. Each one takes a few minutes. Added together they remove two or three hours from every shift, while line speed figures hide them entirely.
The OEE Formula Worth Writing Down
OEE is availability times performance times quality. A line that runs 85 percent of planned time, at 90 percent of design speed, with 97 percent good parts scores 0.85 x 0.90 x 0.97, which is 74 percent. Most rack plants sit between 55 and 70 percent, not because the machine is slow but because planned time leaks away in short stops.
Start With a Baseline This Week
This guide names each of the six losses, gives the minutes measured on delivered lines and sets out a baseline formula you can use right away. OEE makes the stops visible so you know where to act first.