Why First Article Inspection Is Different
A first article inspection record is a one time dimension verification, not a running quality log. Inline inspection watches the line while it runs, while the first article record freezes one setup and attaches a signature to it. It asks one question: does the first good part match the drawing, and can the recipe be locked?
Prepare the Drawing, Coil and Samples
Review the drawing and assign balloon numbers, usually 8 to 14 characteristics with a nominal and tolerance beside each. Read the coil certificate and measure strip thickness at three points, treating a band such as 1.48 to 1.52 mm as an input, because roll gap and inside radius depend on it. Then cut and label three samples from the start, middle and end of the coil, since the three reveal drift a single piece would hide.
Record the Dimensions
Measure web width, flange height, bend angle and inside radius, such as an 80.0 mm web and a 1.5 mm inside radius. The inside radius sets section strength and coating strain at the corner. Then record cut length and hole position, such as 6000 mm within plus or minus 2 mm and a hole 250 mm from the leading edge within plus or minus 1 mm.
Surface, Sign-Off and Recipe Freeze
Inspect all three samples under good light for scratches, cracks, peeling and roll marks. Write the acceptance result, the sign-off name and date, and lock the recipe values for roll gap, line speed and overbend. The sign-off turns readings into a released setup, and it happens only after the three coil positions agree.